Project Overview
This customer had a need to replace existing 50+ year old industrial watertube boilers with new – in addition to low NOx burners & PLC based controls.
Equipment Selected
Three (3) Cleaver-Brooks Model NB-300D-70, 90,000 PPH each at 250 PSI design & 175 PSI operating pressure
Solution & Results
All three (3) boilers delivered on-time; project installed, started, and system fully commissioned within schedule. Low NOx levels exceed expectations. The owner was pleased with overall project outcome.
Completion Date
2018
Project Management
Sales Engineer: Mike Conley
Project Engineer: Brian Frank
Authored By
Mike Conley