Project Overview
An automobile manufacture was purchasing high pressure steam from a nearby facility. The incoming line was beginning to show signs of wear and failure. The options were to fix the existing line or bring the production in house.
Equipment Selected
(2) Cleaver Brooks CBLE boilers, Deaerator, Surge and Flue Stack
Solution & Results
DJ Conley’s design team decided the return on Investment was favorable to bring production in house. The site had an unused room that could be utilized as new boiler room, allowing our design recommendation to take shape! The room was fully BIM (Building Information Modeling) coordinated before any equipment arrived on site.
Completion Date
April, 2022
Project Management
Eric Cameron / Patrick Michels
Authored By
Patrick Michels